Groundworker suffers burns during poorly planned dig

A contractor and its groundworks subbie have been fined £400,000 after unsafe excavation work left a worker with serious burns to his hand and arm.

High Wycombe Magistrates’ Court heard that, on the 2 August 2018, a groundworker was preparing the ground to install a post to carry an Automatic Number Plate Recognition Camera at Twyford near Reading, Berkshire.

Initially, the worker hand dug then started to use an 110V mechanical electric breaker when he struck a power cable supplying an adjacent British Telecommunications building.

The voltage of the cable was 415v causing the ground worker to receive an electric shock that caused burns to one hand and to his opposite arm.

An HSE investigation found that site plans for buried cables had not been consulted and a cable avoidance tool had not been used to locate buried services in advance of carrying out the work.

In addition, there was a lack of properly trained labour and supervision in place for the excavation works.

The principal contractor on site had failed to plan, manage and monitor the excavation works and also failed to provide adequate supervision for the project.

CLC Contractors Limited of Southampton pleaded guilty to breaching CDM regulations and were fined £400,000.00 and ordered to pay costs of £5,300.00.

Subcontractor Paul Gale, Company Director of PAG Building Services Ltd of Southampton also pleaded guilty to safety breaches

Due to the seriousness of the offence the case was referred to Aylesbury Crown Court where Gale was sentenced to 14 months imprisonment suspended for 24 months and 150 hour of community service. HSE was awarded costs of £7,200.

Speaking after the case, HSE inspector John Caboche said: “Those in control of work have a responsibility to devise safe methods of working and to provide the necessary information, instruction and training to their workers in the safe system of working.

“In this instance, readily available buried service records were not consulted, and a cable avoidance tool was not provided to the groundworks team. Utilising these simple steps would have prevented this serious incident.”